PROJECT AT A GLANCE
The job was straightforward on paper: take the transformer off the truck and set it in its final position. In practice, a lift this heavy calls for careful planning at every step: lift calculations, ground conditions, rigging selection, crane setup and clear communication between the crane operator, riggers and the customer's team on site.
For this lift we mobilized our Terex AC 250, a 300-ton all-terrain crane, rigged with its full 213,000 lbs. of counterweight. Running the crane fully counterweighted gave us the capacity and stability margin we wanted for a load of this size, along with the reach to pick the transformer from the trailer and place it precisely where it needed to go.
Every heavy lift starts long before the crane arrives. Our team reviewed the site layout, planned the crane position and swing path, and selected rigging rated well above the load. On lift day, the crew set up the crane, installed the counterweight, rigged the transformer and completed the offload and set in a controlled, methodical sequence. Safety came first at every stage.
Transformers are critical, high-value equipment, and the margin for error when handling them is small. Projects like this are where experienced people and the right crane make the difference. We're proud of our crew's work in Franklin and grateful to our customer for trusting Tri-State Rigging with the lift.
.avif)

.avif)